Back to projects

HVAC; Handwashing and Washrooms; Online Learning Support; New Portable; Building Ventilation Controls; Creating New Classroom Space

St. Catharines, Ontario

completeVentilationCVRIS
Federal contribution
$7.8M
$7,831,194
Federal share80%

of $9.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 25, 2021(actual)
Construction end
Dec 31, 2023(actual)

Also in St. Catharines

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58660 in the federal list. How to read these figures.