Purchase two buses to replace two existing buses to meet ridership demands

Temiskaming Shores, Ontario

completePublic TransitPTIF
Federal contribution
$257,955
Federal share27%

of $970.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2017
2017
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Temiskaming Shores
Construction start
Dec 20, 2016(actual)
Construction end
Mar 23, 2017(actual)

Against the original forecast

  • Construction start3 months earlyforecast Mar 23, 2017
  • Construction end11 months earlyforecast Mar 1, 2018

Also in Temiskaming Shores

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47903 in the federal list. How to read these figures.