Install a new hoist to replace existing bus hoist
Federal contribution
$40,000
Federal share40%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Welland
- Construction start
- Jan 1, 2017(actual)
- Construction end
- Feb 15, 2018(actual)
Against the original forecast
- Construction end8 weeks lateforecast Dec 20, 2017
Also in Welland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47931 in the federal list. How to read these figures.