Refurbish existing bus wash system

Welland, Ontario

completePublic TransitPTIF
Federal contribution
$40,000
Federal share50%

of $80.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Welland
Construction start
Jul 24, 2017(actual)
Construction end
Sep 15, 2017(actual)

Against the original forecast

  • Construction start6 months lateforecast Jan 15, 2017
  • Construction end3 months earlyforecast Dec 20, 2017

Also in Welland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47932 in the federal list. How to read these figures.