Maintenance office and vault room renovations

Welland, Ontario

completePublic TransitPTIF
Federal contribution
$77,322
Federal share50%

of $154.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Welland
Construction start
Jun 1, 2017(actual)
Construction end
Jul 30, 2017(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 15, 2017
  • Construction end5 months earlyforecast Dec 31, 2017