Replace of manual fare boxes with electronic fare boxes on specialized transit vehicles (phase II)
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2017
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Welland
- Construction start
- Jul 28, 2017(actual)
- Construction end
- Aug 31, 2017(actual)
Against the original forecast
- Construction start6 months lateforecast Jan 15, 2017
- Construction end4 months earlyforecast Dec 20, 2017
Also in Welland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47934 in the federal list. How to read these figures.