Back to projects

Improved functionality of farebox through use of technology enhancements

Windsor, Ontario

completePublic TransitPTIF
Federal contribution
$410,672
Federal share50%

of $821.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
201720182019
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Windsor
Construction start
Feb 28, 2017(actual)
Construction end
Jul 31, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Feb 1, 2017
  • Construction end5 months earlyforecast Dec 31, 2019