Two additional Intelligent Transportation System laptops for on road supervisory support vehicles
Federal contribution
$4,375
Federal share49%
of $9.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Windsor
- Construction start
- May 10, 2017(actual)
- Construction end
- Sep 30, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast Feb 1, 2017
- Construction end3 months lateforecast Jun 30, 2017