Implementation of a hybrid bus refurbishing program
Federal contribution
$600,000
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2017201820192020
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Windsor
- Construction start
- Jul 28, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Sep 1, 2017
- Construction end3 months lateforecast Sep 30, 2019
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47991 in the federal list. How to read these figures.