Back to projects

Rehabilitation of concrete surfaces and drains in fuelling and cleaning area of maintenance garage

Windsor, Ontario

completePublic TransitPTIF
Federal contribution
$35,000
Federal share50%

of $70.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Windsor
Construction start
Jun 20, 2017(actual)
Construction end
Sep 30, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2017

Also in Windsor