Renovations and enhancements to customer service area at the main transit terminal
Federal contribution
$20,000
Federal share50%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
201720182019
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Windsor
- Construction start
- May 16, 2017(actual)
- Construction end
- Jun 30, 2019(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2017
- Construction end6 months lateforecast Dec 31, 2018