Acquisition of a commercial grade floor sweeper for maintenance garage floor

Windsor, Ontario

completePublic TransitPTIF
Federal contribution
$42,500
Federal share50%

of $85.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Windsor
Construction start
Apr 11, 2017(actual)
Construction end
Sep 30, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Feb 1, 2017
  • Construction end3 months lateforecast Jun 30, 2017

Also in Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48000 in the federal list. How to read these figures.