Back to projects

Acquisition of a commercial grade parts washer for maintenance garage

Windsor, Ontario

completePublic TransitPTIF
Federal contribution
$37,500
Federal share50%

of $75.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Windsor
Construction start
Apr 12, 2017(actual)
Construction end
Nov 30, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Feb 1, 2017
  • Construction end4 weeks earlyforecast Dec 31, 2017

Also in Windsor