Cycling-Transit Connection on Malden Road - Armanda to South City Limits
Federal contribution
$250,000
Federal share50%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Windsor
- Construction start
- Oct 17, 2017(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Mar 1, 2017
- Construction end2 months earlyforecast Dec 31, 2018
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48007 in the federal list. How to read these figures.