Cycling-Transit Connection on Kamloops Street - Calderwood to the West Limit

Windsor, Ontario

completeActive TransportationPTIF
Federal contribution
$23,460
Federal share49%

of $47.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20172019202120232025
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Windsor
Construction start
Oct 2, 2017(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 1, 2017
  • Construction end21 months lateforecast Jun 30, 2023