Eighteen (18) 21 to 22 foot buses for Accessible Transit
St. John's, Newfoundland and Labrador
Federal contribution
$753,548
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 3, 2017
2017
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Province of Newfoundland and Labrador
- Construction start
- Feb 13, 2017(actual)
- Construction end
- Jul 31, 2017(actual)
Against the original forecast
- Construction start3 months earlyforecast May 1, 2017
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48011 in the federal list. How to read these figures.