Chlorination Upgrade and Pumphouse Upgrades
Port Albert, Newfoundland and Labrador
Federal contribution
$41,709
Federal share50%
of $83.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2016
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Local Service District of Port Albert
- Construction start
- Sep 25, 2017(actual)
- Construction end
- Jun 1, 2018(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 15, 2017
- Construction end10 months earlyforecast Mar 31, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48013 in the federal list. How to read these figures.