Back to projects

Chlorination Upgrade and Pumphouse Upgrades

Port Albert, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$41,709
Federal share50%

of $83.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 25, 2017(actual)
Construction end
Jun 1, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 15, 2017
  • Construction end10 months earlyforecast Mar 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48013 in the federal list. How to read these figures.