Watermain replacement on King St from Arthur St to Dunlop St., James St from Kings St. to Centre St., & Ontario St. W. from Henry St. to King St.

Durham, Ontario

completeDrinking WaterCWWF
Federal contribution
$611,395
Federal share49%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 15, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2017
  • Construction end2.8 years earlyforecast Sep 30, 2021