Watermain replacement crossing Hwy 401 east of Brock St.

Durham, Ontario

completeDrinking WaterCWWF
Federal contribution
$800,000
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020202120222023
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 30, 2017(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 1, 2017