Watermain extension on Regional Rd. 25 (Consumers Dr.) from east of Thickson Rd. to Thornton Rd.

Durham, Ontario

completeDrinking WaterCWWF
Federal contribution
$543,791
Federal share49%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 30, 2018(actual)
Construction end
Jun 8, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Jun 1, 2017
  • Construction end22 months earlyforecast Mar 31, 2020