Watermain extension on Regional Rd. 25 (Consumers Dr.) from east of Thickson Rd. to Thornton Rd.
Federal contribution
$543,791
Federal share49%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Durham
- Construction start
- Jan 30, 2018(actual)
- Construction end
- Jun 8, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Jun 1, 2017
- Construction end22 months earlyforecast Mar 31, 2020
Also in Durham
- Construction of Median Bus Rapid Transit Lanes on Highway 2, City of Pickering$45.8M
- Detailed Design and Construction of Bus Rapid Transit (BRT) Lanes in the Town of Ajax, Town of Whitby and City of Oshawa$23.5M
- Harmony Creek Water Pollution Control Plant Upgrades$7.8M
- Durham Region Transit Fleet Replacements - 24 conventional buses$5.9M
- Demolition and New Construction of Durham Region Transit Operations Building$5.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48022 in the federal list. How to read these figures.