Sanitary sewer extension on Regional Rd. 52 (Thornton Rd.) from Champlain Ave. to Consumers Dr.

Durham, Ontario

completeWastewaterCWWF
Federal contribution
$205,000
Federal share50%

of $410.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 30, 2017(actual)
Construction end
Feb 9, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2017
  • Construction end24 months earlyforecast Feb 8, 2020

Also in Durham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48023 in the federal list. How to read these figures.