Oshawa Water Supply Plant - Plant No. 1 - Filter Rehabilitation

Durham, Ontario

completeDrinking WaterCWWF
Federal contribution
$1.6M
$1,600,000
Federal share50%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018201920202021
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 12, 2017(actual)
Construction end
Feb 4, 2021(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 1, 2017
  • Construction end2 months lateforecast Nov 30, 2020

Also in Durham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48026 in the federal list. How to read these figures.