Polybutylene Water Service Replacement Program (City of Pickering and Town of Ajax)
Federal contribution
$2.5M
$2,534,618
Federal share48%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 23, 2017
ApprovedMar 27, 2018
20182019
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Durham
- Construction start
- Jun 30, 2017(actual)
- Construction end
- Mar 1, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2017
- Construction end13 months earlyforecast Mar 31, 2020
Also in Durham
- Construction of Median Bus Rapid Transit Lanes on Highway 2, City of Pickering$45.8M
- Detailed Design and Construction of Bus Rapid Transit (BRT) Lanes in the Town of Ajax, Town of Whitby and City of Oshawa$23.5M
- Harmony Creek Water Pollution Control Plant Upgrades$7.8M
- Durham Region Transit Fleet Replacements - 24 conventional buses$5.9M
- Demolition and New Construction of Durham Region Transit Operations Building$5.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48032 in the federal list. How to read these figures.