Chlorination/PRV Building Upgrade

South River, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$6,280
Federal share15%

of $42.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of South River
Construction start
Aug 7, 2017(actual)
Construction end
Nov 26, 2018(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Aug 31, 2017
  • Construction end11 months lateforecast Dec 31, 2017

Also in South River