Early works in support of the development of a Storm Water Master Plan

Brock, Ontario

completeWastewaterCWWF
Federal contribution
$47,465
Federal share32%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018201920202021
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Brock
Construction start
Dec 1, 2017(actual)
Construction end
Dec 7, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast Dec 1, 2016
  • Construction end2 months lateforecast Sep 30, 2020

Also in Brock

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48044 in the federal list. How to read these figures.