Public Access Extension for Designated Bus Stops
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2017
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Town of Penetanguishene
- Construction start
- May 3, 2017(actual)
- Construction end
- Oct 30, 2017(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 5, 2017
Also in Penetanguishene
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48093 in the federal list. How to read these figures.