Back to projects

Purchase Handivan Expansion Fleet (2 new buses)

Burlington, Ontario

completePublic TransitPTIF
Federal contribution
$151,189
Federal share38%

of $401.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Burlington
Construction start
May 15, 2017(actual)
Construction end
Oct 16, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Mar 1, 2017
  • Construction end2 weeks earlyforecast Oct 31, 2017

Also in Burlington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48097 in the federal list. How to read these figures.