Building Automation System Upgrade

Burlington, Ontario

completePublic TransitPTIF
Federal contribution
$35,000
Federal share50%

of $70.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Burlington
Construction start
Feb 2, 2018(actual)
Construction end
Mar 12, 2018(actual)

Against the original forecast

  • Construction start9 months lateforecast May 1, 2017
  • Construction end7 weeks earlyforecast Apr 30, 2018

Also in Burlington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48101 in the federal list. How to read these figures.