Conversion of Bus Bay Lighting to Light-Emitting Diode (LED)

Burlington, Ontario

completePublic TransitPTIF
Federal contribution
$29,744
Federal share24%

of $125.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Burlington
Construction start
Dec 4, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Oct 1, 2017
  • Construction end9 months lateforecast Jan 31, 2018