Construction of a concrete sidewalk on John Lucas Drive
Federal contribution
$157,021
Federal share33%
of $480.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Burlington
- Construction start
- Jul 31, 2017(actual)
- Construction end
- Aug 25, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2017
- Construction end5 weeks earlyforecast Oct 1, 2017
Also in Burlington
- Halton Region Wastewater Treatment (Skyway Facility)$51.4M
- Replacement of Access Points; Open Concept Schools; Building Automation Systems & Controls Upgrade; Child Care Retrofits & Outdoor Spaces$6.9M
- Portable Classroom Ventilation Improvements; HVAC Improvements; Window Replacement$5.6M
- Improvements to HVAC, Windows, Bottle Filling Stations, Washrooms, Doors, Child Care Centre, WiFi and Network Infrastructure$5.4M
- Highway 403 - Rehabilitation and Resurfacing$4.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48105 in the federal list. How to read these figures.