Integrated Bus Arrival Display Signs at Aldershot, Burlington and Appleby GO stations

Burlington, Ontario

completePublic TransitPTIF
Federal contribution
$28,147
Federal share28%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017201820192020
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Burlington
Construction start
Aug 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2017
  • Construction end11 months lateforecast Apr 30, 2019