Elgin Promenade Multi Use Pathway - Phase 3 (John St. to Brant St.)

Burlington, Ontario

completeActive TransportationPTIF
Federal contribution
$372,253
Federal share42%

of $876.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Burlington
Construction start
Sep 18, 2017(actual)
Construction end
May 1, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 1, 2017