Schedule

Announced and approvedJan 20, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Tide Head
Construction start
May 23, 2017(actual)
Construction end
Sep 15, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2017
  • Construction end8 months earlyforecast May 31, 2018

Also in Tide Head