Back to projects

Upgrade of Penstock for Lift Station No. 4

Rogersville, New Brunswick

completeWastewaterCWWF
Federal contribution
$136,055
Federal share46%

of $296.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Rogersville
Construction start
Oct 10, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2017
  • Construction end2 weeks lateforecast Jun 15, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48188 in the federal list. How to read these figures.