Back to projects

Storm water sewer - LeBouthillier Street

Bas-Caraquet, New Brunswick

completeWastewaterCWWF
Federal contribution
$241,781
Federal share48%

of $504.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Bas-Caraquet
Construction start
Sep 27, 2017(actual)
Construction end
Dec 5, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2017
  • Construction end4 months lateforecast Jul 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48197 in the federal list. How to read these figures.