Study and Design for Water Supply and Sewer Systems
Federal contribution
$18,809
Federal share50%
of $37.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Bertrand
- Construction start
- Apr 29, 2016(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction end22 months lateforecast May 20, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48214 in the federal list. How to read these figures.