Back to projects

Environmental Risk Assessment for Lagoon

Saint-Hilaire, New Brunswick

completeCapacity BuildingCWWF
Federal contribution
$5,190
Federal share46%

of $11.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Saint-Hilaire
Construction start
Dec 1, 2016(actual)
Construction end
Aug 8, 2017(actual)

Against the original forecast

  • Construction end17 months earlyforecast Dec 31, 2018

Also in Saint-Hilaire

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48219 in the federal list. How to read these figures.