Environmental Risk Assessment for Lagoon
Federal contribution
$5,190
Federal share46%
of $11.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Saint-Hilaire
- Construction start
- Dec 1, 2016(actual)
- Construction end
- Aug 8, 2017(actual)
Against the original forecast
- Construction end17 months earlyforecast Dec 31, 2018