Back to projects

Decommission and Replace Rennie Road Standpipe with Transmission Line to New Water Reservoir

Miramichi, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$728,522
Federal share49%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Miramichi
Construction start
Sep 8, 2017(actual)
Construction end
Aug 30, 2019(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 1, 2017
  • Construction end8 months lateforecast Dec 31, 2018

Also in Miramichi

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48229 in the federal list. How to read these figures.