Decommission and Replace Rennie Road Standpipe with Transmission Line to New Water Reservoir
Federal contribution
$728,522
Federal share49%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Miramichi
- Construction start
- Sep 8, 2017(actual)
- Construction end
- Aug 30, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 1, 2017
- Construction end8 months lateforecast Dec 31, 2018