Consolidation of Water Chlorination for Chatham Distribution System Phase 1
Federal contribution
$990,582
Federal share50%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Miramichi
- Construction start
- Sep 30, 2017(actual)
- Construction end
- Nov 30, 2019(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2017
Also in Miramichi