Construction of a drinking water main for Lac-du-Camp-Droit and part of Rue Champigny

Larouche, Quebec

completeDrinking WaterCWWF
Federal contribution
$481,573
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
2017
Built

Approved 5 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Larouche
Construction start
Apr 1, 2017(actual)
Construction end
Sep 15, 2017(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 3, 2016
  • Construction end6 months earlyforecast Mar 31, 2018