Extension of the drinking water main - Sector 2 (2.627 km)

Saint-Henri-de-Taillon, Quebec

completeDrinking WaterCWWF
Federal contribution
$240,109
Federal share31%

of $763.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
2017
Built

Approved 5 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 10, 2017(actual)
Construction end
Nov 25, 2017(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 5, 2017
  • Construction end16 months earlyforecast Mar 31, 2019

Also in Saint-Henri-de-Taillon