Back to projects

Upgrading the Wastewater Treatment Plant

Verchères, Quebec

completeWastewaterCWWF
Federal contribution
$189,102
Federal share50%

of $379.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 24, 2017
20172018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Verchères
Construction start
Sep 1, 2017(actual)
Construction end
Jun 28, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 2, 2017
  • Construction end9 months earlyforecast Mar 31, 2019

Also in Verchères