Upgrading of the P1 and P2 sewer pumping stations -optimization of storm overflow structures
Federal contribution
$1.3M
$1,263,846
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 10, 2017
2017201820192020
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Chibougamau
- Construction start
- May 28, 2018(actual)
- Construction end
- Feb 17, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 5, 2018
- Construction end7 weeks lateforecast Dec 31, 2019
Also in Chibougamau