Back to projects

Upgrading of the P1 and P2 sewer pumping stations -optimization of storm overflow structures

Chibougamau, Quebec

completeWastewaterCWWF
Federal contribution
$1.3M
$1,263,846
Federal share50%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 10, 2017
2017201820192020
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Chibougamau
Construction start
May 28, 2018(actual)
Construction end
Feb 17, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 5, 2018
  • Construction end7 weeks lateforecast Dec 31, 2019

Also in Chibougamau