Upgrading of the water supply system and extension of services - Highway 132
Federal contribution
$3.2M
$3,238,075
Federal share50%
of $6.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 3, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Sayabec
- Construction start
- Sep 7, 2017(actual)
- Construction end
- Nov 16, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 15, 2017
- Construction end2 weeks earlyforecast Nov 30, 2018
Also in Sayabec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48263 in the federal list. How to read these figures.