Extension of sanitary sewer services - Highway 108

Saint-Victor, Quebec

completeWastewaterCWWF
Federal contribution
$430,499
Federal share38%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2017
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 7, 2017(actual)
Construction end
Nov 30, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast May 22, 2017
  • Construction end16 months earlyforecast Mar 31, 2019

Also in Saint-Victor