Extension of sanitary sewer services - Highway 108
Federal contribution
$430,499
Federal share38%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2017
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Saint-Victor
- Construction start
- Aug 7, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast May 22, 2017
- Construction end16 months earlyforecast Mar 31, 2019
Also in Saint-Victor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48265 in the federal list. How to read these figures.