Back to projects

Re-directing the collector sewer of the village of Val-Morin to the Val-David treatment plant

Val-Morin, Quebec

completeWastewaterCWWF
Federal contribution
$592,435
Federal share50%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 3, 2017
2017
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Val-Morin
Construction start
Sep 5, 2017(actual)
Construction end
Nov 17, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast May 29, 2017
  • Construction end16 months earlyforecast Mar 31, 2019

Also in Val-Morin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48269 in the federal list. How to read these figures.