Back to projects

Treatment plant upgrade

Sainte-Angèle-de-Monnoir, Quebec

completeWastewaterCWWF
Federal contribution
$762,642
Federal share47%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 24, 2017
201720182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Nov 13, 2017(actual)
Construction end
Aug 6, 2019(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2017
  • Construction end2 months lateforecast May 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48272 in the federal list. How to read these figures.