Upgrading of drinking water treatment / Pied-de-la-Montagne area

Saint-Casimir, Quebec

completeDrinking WaterCWWF
Federal contribution
$771,573
Federal share49%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
20172018
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 11, 2017(actual)
Construction end
Aug 22, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2017
  • Construction end7 months earlyforecast Mar 31, 2019

Also in Saint-Casimir

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48273 in the federal list. How to read these figures.