Pollux Crescent Phase 1 - Water & Sewer Upgrade
St. Lawrence, Newfoundland and Labrador
Federal contribution
$204,118
Federal share33%
of $613.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 3, 2017
2018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of St. Lawrence
- Construction start
- Oct 16, 2017(actual)
- Construction end
- Jun 11, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 1, 2017
- Construction end6 months lateforecast Nov 30, 2017
Also in St. Lawrence
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48276 in the federal list. How to read these figures.