Design and construction of accessibility conversions for 27 existing bus stops.
Federal contribution
$11,666
Federal share9%
of $125.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2017
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Kawartha Lakes
- Construction start
- Oct 5, 2017(actual)
- Construction end
- Dec 8, 2017(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 28, 2018